Gov’t Announces 98% Compensation for EACOP-Affected Persons, First Oil Expected in July
March 13, 2026

Compensation for persons affected by the East African Crude Oil Pipeline (EACOP) project has reached 98 per cent completion, according to Peninah Aheebwa, Director for Economic and National Content Monitoring at the Petroleum Authority of Uganda (PAU).
The update came after concerns raised by Joseph Ssewungu, Member of Parliament for Kalungu West County, who warned about unresolved grievances among some affected persons.
“There are some people who have been raising issues of compensation… We have seen challenges like vandalism in Nigeria’s oil mining industry, which we need to avoid here,” Ssewungu said.
Aheebwa told lawmakers that compensation was conducted in accordance with national laws and standards set by the International Finance Corporation, widely regarded as a global benchmark for managing environmental and social risks in private-sector projects.
“Everyone has been compensated to the best of their satisfaction, in our view. This is highly monitored by the lenders of this project,” she noted.
She made the remarks while appearing before the Public Accounts Committee (Central Government) on March 11, 2026.
Uganda is now targeting first oil by the end of July 2026, a milestone marking the start of commercial production and export of crude.
Progress on upstream projects is ahead of minimum requirements:
Tilenga Project: 198 wells drilled (170 required for first oil)
Kingfisher Project: 21 wells drilled (19 required)
Aheebwa added that construction progress stands at:
Tilenga central processing facilities and feeder pipelines — 67% complete
Kingfisher — 77% complete
EACOP pipeline — 81% complete
To meet the tight timeline, work shifts on Tilenga have been increased to three eight-hour rotations daily.
During the session, Basil Bataringaya, MP for Kashari North County, pressed PAU on delays in auditing costs recoverable by oil companies.
Aheebwa revealed that approximately US$12.3 billion has been invested in Uganda’s petroleum sector to date, though not all expenditures qualify for cost recovery.
For the pipeline specifically:
US$3.5 billion has already been spent on EACOP
Costs will be recouped through a transport tariff of US$12.77 per barrel
A 2021 report from the Auditor General of Uganda reviewed cost recovery claims totaling US$3.4 billion from companies involved in the projects, including:
TotalEnergies EP Uganda
CNOOC Uganda Limited
Uganda National Oil Company
China Oilfield Services Limited Uganda
Of that amount:
US$2.9 billion (87%) was approved for recovery
US$439 million (13%) was disallowed
However, Aheebwa noted that later investments up to 2025 are not fully covered by the available audit.
With drilling targets exceeded and major infrastructure nearing completion, Uganda’s oil sector is entering a decisive phase. Achieving first oil in 2026 would transform the country into a petroleum exporter and reshape its economic outlook — provided remaining social and financial issues are managed effectively.

UG Diplomat is an independent digital news and media platform dedicated to comprehensive coverage of national politics, regional diplomacy, international relations, geopolitics, defense, and business. Published under Currentarc Media Ltd, we provide authoritative analysis, breaking news, and in-depth reporting on the diplomatic and economic developments shaping East Africa and the global arena.
COMPANY
Contact Us
Privacy Policy
Terms and Conditions
CONTACT INFORMATION
info@ugdiplomat.com
+256774552385
Copyright © 2026 UG Diplomat -Product of CURRENTARC MEDIA